PRINCE2 Foundation Practice: Initiating a Project (IP) (With Mock Questions!)

Hello Future PRINCE2 Experts! 👋

Welcome to your revision guide for the PRINCE2 Foundation Practice: Initiating a Project (IP). I'm here to help you navigate through this important topic with ease and confidence. Let's make this journey engaging and informative!




Overview of Initiating a Project (IP)

Initiating a Project is a vital stage in the PRINCE2 methodology. It sets the groundwork for the entire project, ensuring that everything is planned out meticulously before any actual work begins. This stage ensures that all stakeholders have a clear understanding of the project's objectives, benefits, scope, and risks.


Key Learning Items 📚

In the Initiating a Project process, you'll dive into several critical aspects:

🌟 Establishing project controls and setting up project management structures

🌟 Developing a robust Business Case

🌟 Preparing detailed project plans

🌟 Identifying and assessing risks

🌟 Defining quality expectations and how they will be achieved

🌟 Setting up the Project Initiation Documentation (PID)


Demonstrating Your Knowledge

At the PRINCE2 Foundation level, you need to show that you understand the principles and purpose behind initiating a project. Here's what you should focus on:

✨ Explain the importance of the Business Case and how it is developed

✨ Describe the components and significance of the Project Initiation Documentation (PID)

✨ Identify the steps involved in setting up project controls and management structures

✨ Understand how risks are identified and managed during this phase

✨ Demonstrate knowledge of quality management within the project


Key Things to Remember Before the Exam 📝

Before you walk into that exam room, keep these essentials in mind:

🔑 Review the key components of the PID and their purposes

🔑 Understand the process of creating and maintaining the Business Case

🔑 Familiarize yourself with how project controls are established

🔑 Recall the methods for risk identification and assessment

🔑 Remember the importance of setting quality criteria and how they are managed

Take a deep breath, stay positive, and trust in your preparation!


Mock Questions to Test Your Knowledge

Let's dive into some practice questions to get you exam-ready.

Q1 - What is the main purpose of the Project Initiation Documentation (PID)?

a) To list the project's risks

b) To define the project and serve as a contract between the Project Manager and the Project Board

c) To create the project's Gantt chart

d) To allocate resources to project tasks


Q2 - Which document details why a project is worthwhile and should continue?

a) Project Plan

b) Risk Register

c) Business Case

d) Quality Management Strategy


Q3 - During the Initiating a Project process, who is responsible for producing the Project Plan?

a) Project Board

b) Project Support

c) Project Manager

d) Team Manager


Q4 - What should be established to ensure that the project remains within agreed tolerances?

a) Project controls

b) Risk management strategy

c) Quality management plan

d) Communication plan


Q5 - When should the Project Initiation Documentation (PID) be updated?

a) At the start of each stage

b) Whenever there is a significant change in the project

c) Only at the end of the project

d) It does not need to be updated once approved

Answers and even more questions can be found in our PRINCE2 Foundation Revision Booklet


Good luck with your revision! Remember, understanding the Initiating a Project process is crucial for laying the groundwork for successful project management. You've got this! 🚀